The Breakthrough of Valturska B project is part of our project for the construction of two buildings, right next to the newly constructed part of Valturska Street and the junction with Japodska Street in Šijana. These are five-story buildings, each of which will have 27 apartments, and its own parking lot, with the option of choosing an outdoor or indoor covered parking space. The buildings are located in a very good position, right next to the newly built road, just a few minutes’ walk from Kaufland and Plodin and about 15 minutes to the Pula City Mall shopping center. From the city center, they are separated by a 20-minute walk, and there are also several bus stops nearby, which provides an even better connection with the rest of the city.
- Price : 2400€/m2
- Square meters : 42-58m2
- Deadline for Construction Completion : 2023

Close to public transport

Parking place

Air conditioning

Project Timeline
04/2022 – Start of earthworks and foundation works
05/2022 – Completed foundation slab, start of raising the ground floor
05/2022 – Raising the ground floor
06/2022 – Completed raising of the ground floor, start of raising the first floor
08/2022 – Completion of raising the first floor
09/2022 – Raising the second floor
10/2022 – Completion of raising the second floor
11/2022 – Start of construction of the third floor
11/2022 – Raising the third floor
12/2022 – Completed raising of the third floor, preparations for the start of raising the fourth floor
01/2023 – Start of construction of the fourth floor
02/2023 – Completion of raising the fourth floor
03/2023 – Completed raising of the fourth floor, cleaning of the garden
04/2023 – Works on the roof, partition walls and installations
06/2023 – Mounted cabinets for electric meters
06/2023 – Start of installation of PVC joinery
06/2023 – Works on the garden
07/2023 – Sewage works
08/2023 – Preparations for the start of insulation installation
09/2023 – Installation of insulation
11/2023 – Completed installation of insulation and work on the facade
12/2023 – Laying of stone on the staircase
01/2024 – Works on industrial floors in garages
02/2024 – Start of ceramic installation
03/2024 – Works on landscaping the garden and parking lot