The City Mall A project began construction 06/2020. This is the second building that is being built right next to the Pula City Mall shopping center, and this will complete a larger investment than a total of two identical buildings in the immediate vicinity of this popular shopping center. It is a building with a total of 60 apartments, mostly smaller in size of 42-50 m2 (one separate bedroom), and another 8 two-bedroom apartments in western and southwestern orientation of 55 m2. There will be a small business space on the ground floor available in the building, and at the customer’s request, an outdoor uncovered or indoor covered parking space, ceramics and laminate can be chosen. Of particular note are the 3 entrances to the building, the elevator, comfortable main corridors inside the building, the illuminated internal staircase of the building with a natural light source, and the modern shape of the building with a flat roof. Check the availability of apartments below …
- Square meters : 39-52m2
- Construction completion deadline : 2021
Close to public transport
Parking place
Air conditioned
Project Timeline
05/2020 – Start digging the foundation
06/2020 – Digging and Laying the Foundation
06/2020 – Raising the ground floor
07/2020 – Concreting the ground floor
08/2020 – Completion of concreting the ground floor, start of raising the first floor
09/2020 – Erection and construction of the first floor
10/2020 – Demonstration of the continuation of the erection of the building
10/2020 – Concreting the slab of the first floor of the building, continuation of construction
10/2020 – Concrete slab of the first floor, raising the second floor
11/2020 – Continuation of the construction of the second floor
11/2020 – Concreting the slab of the second floor of the building
12/2020 – Erection and construction of the third floor
02/2021 – Completion of the third floor, preparation for casting the fourth floor slab
03/2021 – Erection and construction of the fourth floor
04/2021 – Pouring concrete of the first part of the roof slab
04/2021 – The second part of the roof slab was poured, the erection of the building was completed
04/2021 – Start of installation of PVC joinery
05/2021 – Installation of PVC joinery
07/2021 – Completed installation of PVC joinery, installation of electrical installations
08/2021 – Start of plastering apartments
09/2021 – Preparations for starting the installation of insulation
11/2021 – Start of insulation installation
12/2021 – Installation of insulation
02/2022 – Completion of insulation installation
07/2022 – Facade painting
08/2022 – Interior works, installation of ceramics
08/2022 – Works on landscaping the garden
08/2022 – Sewer connection works
09/2022 – Works on the decoration of the entrance area and garden
10/2022 – Completed facade painting
10/2022 – Installation of ceramics