The Breakthrough of Valturska A project is part of our project of building two buildings, right next to the newly built part of Valturska Street and the junction with Japodska Street in Šijana. These are five-storey buildings, each of which will have 27 apartments, and its own parking lot, with the possibility of choosing an outdoor or indoor covered parking space. The buildings are located in a very good position, right next to the newly built road, just a few minutes walk from Kaufland and Plodine and 15 minutes to the shopping center Pula City Mall. From the city center, they are separated by a 20-minute walk, and there are several bus stops nearby, which provides even better connections with the rest of the city.
- Price : 2700€/m2
- Square meters : 42-58m2
- Construction Completion Deadline : 2022
Close to public transport
Parking place
Air conditioning
Project Timeline
09/2021 – Beginning of preparatory earthworks
09/2021 – Commencement of works on the foundations
09/2021 – Concreting of foundations
09/2021 – Works on foundations
10/2021 – Works on foundations
10/2021 – Concreting the foundation slab
10/2021 – Ground floor construction
11/2021 – Preparations for concreting the first floor slab
11/2021 – Concreting of the first floor slab
12/2021 – Raising the first floor
12/2021 – completion of the first floor
01/2022 – Raising the second floor
02/2022 – Completion of the second floor, start of the third floor
03/2022 – Raising the third floor
03/2022 – Completion of the third floor, preparations for the start of the fourth floor
04/2022 – Start of construction of the fourth floor
04/2022 – Raising the fourth floor
04/2022 – Completion of the fourth floor
05/2022 – Start of installation of PVC joinery
06/2022 – Finished installation of PVC joinery
07/2022 – Start of installation of insulation
08/2022 – Installation of insulation
09/2022 – Plastering of apartments
09/2022 – Coating of silicate
10/2022 – Beginning of facade painting
11/2022 – Facade painting
12/2022 – Completed facade painting
12/2022 – Painting of apartments, interior works
01/2023 – Installation of ceramics
02/2023 – Start of stone laying
03/2023 – Stone placement
05/2023 – Installation of the fence