The Bonus 5 building is part of our project at the very end of Japodska Street, at the intersection with Bože Gumpeca Street, and is identical to its predecessor, the Bonus 4 Building. It is a multi-storey building with an elevator near the shopping and business zone in Pula. In addition to the proximity of all shopping centers, from this position there is a very easy and quick access to the city center, and only 5 minutes walk to the popular shopping center Pula City Mall. The building will be connected to the city gas, and will have a total of 60 apartments
- Quadrature : 38-58m2
- Construction completion deadline : 2021
Parking
Close to public transport
Air conditioning
Project Timeline
08/2019 – Laying the foundation
09/2019 – Ground floor construction
10/2019 – Raising the first floor
11/2019 – Raising the second floor
12/2019- Raising the third floor
01/2020 – Raising the fourth floor
02/2020 – Completion of the construction of the fourth floor, attic works
03/2020 – Installation setup
04/2020 – Beginning of works on the yard
06/2020 – Roof works
07/2020 – Installation of carpentry
07/2020 – Continuation of work on the roof
09/2020 – Preparations for installation of insulation and facade
10/2020 – Delivery of insulation and facade
10/2020 – Works on installation of insulation and preparation for the facade
11/2020 – Completion of insulation installation
12/2020 – Installation of insulation completed
02/2021 – Completion of plastering the building
03/2021 – Facade painting
04/2021 – Finished painting of the facade, works on concrete substrates and plastering
05/2021 – Plastering of stairs, interior works
06/2021 – Start of work on the yard
07/2021 – Start of ceramics installation
08/2021 – Installation of ceramics, interior decoration
11/2021 – Works on the fence wall
12/2021 – Sewer connection works
01/2022 – Completed works on the connection of the sewage system, beginning of the decoration of the entrance area
02/2022 – Arrangement of the entrance area
04/2022 – Landscaping
07/2022 – Asphalting of the parking lot
10/2022 – Marked parking spaces