The Lenox project is another in a series of our apartment buildings. It is a multi-storey building near the tourist resort Verudela, not far from the most popular beaches in Pula, and its accommodation in Monte Paradiso Street, in addition to the proximity of beaches and Verudela, provides relatively easy and quick access to the city center. Apart from the proximity to very attractive facilities, what makes this building special is that from the ground floor there is a beautiful view of the sea and the Pula Marina.
- Price : 3000 - 3500€/m2
- Square meters : 38-80m2
- Completion Deadline : 2022
Parking
Air conditioned
Close to public transport
Close to the Beach / Sea View
Project Timeline
03/2020 – Preparatory works
03/2020 – Leveling the terrain, and preparation for laying the foundation
08/2020 – Start of work on the basement
08/2020 – Raising the basement
09/2020 – Raising the basement
10/2020 – completion of basement construction, preparations for ground floor construction
11/2020 – Start of ground floor construction
01/2021 – Raising the ground floor
02/2021 – Continuation of the ground floor construction
03/2021 – Concreting the ground floor
04/2021 – Preparations for casting the ground floor slab and starting the construction of the first floor
04/2021 – Start of construction of the first floor of the building
05/2021 – Raising the first floor
06/2021 – Raising the second floor
08/2021 – Second floor erection completed, third floor erection
09/2021 – Completion of the third floor, start of the fourth floor
10/2021 – Raising the fourth floor, installing PVC joinery
11/2021 – Beginning of the construction of the fifth floor
12/2021 – Raising the fifth floor
12/2021 – Completion of the fifth floor
01/2022 – Concreting the roof
02/2022 – Concreting of the roof completed
03/2022 – Installation work
06/2022 – Completed installation of PVC joinery
07/2022 – Start of installation of insulation
08/2022 – Works on concrete surfaces
09/2022 – Start of ceramic installation
10/2022 – Coating of silicate, works on the facade
11/2022 – Installation of ceramics on balconies, interior works
02/2023 – Painting of the facade, completion of works on the facade
04/2023 – Laying stone on the stairs
05/2023 – Works on the second phase of electrical installations
06/2023 – Installation of glass fences on the balconies