Kaštanjer Street Buildings E and F
The buildings of Kaštanjer E and F Street are part of our project for the construction of a residential area that will consist of 17 smaller, nice buildings, which will have 4 apartments, which is an advantage for those who like buildings with a smaller number of apartments. The project will be completed with the construction of a turnaround, positioned in the middle of the settlement, and will connect to Kaštanjer Street and thus provide easy and comfortable access to each of the buildings.
- Square meters : 45-109m2
- Construction Completion Deadline : 2021
Close to public transport
Parking
Air conditioning
Project Timeline
11/2019 – Start of construction
12/2019 – Laid foundations, raising the ground floor
02/2020 – Raised ground floor, preparations for raising the first floor
03/2020 – Raising the first floor
05/2020 – Raising the first floor
06/2020 – Raising the second floor
07/2020 – Second floor erected, roof works
03/2021 – Installation of PVC joinery
05/2021 – Installation of insulation and facade
06/2021 – Abschluss der Dämmung
07/2021 – Plastering the building
07/2021 – Silicate coating
08/2021 – Facade painting
09/2021 – Finished painting of the facade, preparations for the installation of ceramics
10/2021 – Installation of ceramics
11/2021 – Laying of stone
12/2021 – Works on connection of water and sewage
02/2022 – Completed works on the garden