Project – Block 6
Project Block 6 is our latest project to build a larger multi-storey building on Monvidal. The building is located near the shopping and business zone in Pula, and is close to our previous projects on Monvidal, Bonus 4 and 5. It is a larger building that will have about 60 apartments located in a convenient position just ten minutes walk from the shopping center Pula City Mall, and from the city center is a 5-minute bus ride away. In addition to the shopping center, near the building there are a number of supermarkets such as Lidl, Kaufland and Plodine.
- Price : 2600€/m2
- Square meters : 34-70m2
- Construction completion deadline : 2022
Close to public transport
Parking place
Air conditioning
Project Timeline
08/2021 – Beginning of preparatory earthworks
08/2021 – Preparatory earthworks
09/2021 – Commencement of works on the foundations
09/2021 – Works on foundations
09/2021 – Works on foundations
09/2021 – Casting of the foundation slab
10/2021 – Start of ground floor construction
10/2021 – Ground floor construction
10/2021 – Ground floor construction
11/2021 – Concreting the first half of the first floor slab
11/2021 – Start of construction of the first floor
11/2021 – Raising the first floor
12/2021 – Completion of the first floor
12/2021 – Start of construction of the second floor
12/2021 – Raising the second floor
01/2022 – Completion of the second floor
01/2022 – Start of construction of the third floor
02/2022 – Raising the third floor
02/2022 – The beginning of the construction of the fourth floor
03/2022 – Raising the fourth floor
03/2022 – Completion of the construction of the fourth floor, the beginning of the construction of the attic
04/2022 – Raising the attic
05/2022 – Completion of attic construction, start of roof works
06/2022 – Roof works
08/2022 – Installation of PVC joinery
09/2022 – Finished installation of PVC joinery, works on the fence wall
10/2022 – Installation of insulation
11/2022 – Finished installation of insulation, start of plastering the building, interior works
12/2022 – Finished plastering of the building, preparations to start painting the facade
01/2023 – Facade painting
02/2023 – Completed facade painting
03/2023 – Start of laying stone and ceramics
04/2023 – Installation of ceramics
06/2023 – Beginning of landscaping of the garden and parking lot
07/2023 – Asphalted parking, marked parking spaces
08/2023 – Finished installation of the railing in the stairwells