The Villas Park 3 project is another of our projects in Valdebek, and it is about the construction of a smaller settlement of fifteen buildings, located near our project “Valdebek – Modrušanov Prilaz”. The village is in a quiet, great position, and close to two pizzerias, two markets and a bus station that takes you a ten minute drive to the center of Pula. Buildings 3 and 4 are one of the first buildings of this future settlement, also the first to start construction, and they are smaller buildings, which is ideal for those who like a smaller number of neighbors.
- Square meters : 42-51m2
- Construction completion deadline : 2021

Close to public transport

Parking

Air conditioning

Project Timeline
05/2020 – Start of construction
06/2020 – Raising the ground floor
07/2020 – Raised ground floor, raising the first floor
08/2020 – Completion of the first floor
10/2020 – Raising the second floor
11/2020 – Completion of the second floor, preparations for roof works
01/2021 – Roof works
02/2021 – Start of concreting the roof
02/2021 – Finishing the roof concreting
03/2021 – Installation of PVC joinery
06/2021 – Start of insulation installation
07/2021 – Installation of insulation
08/2021 – Installation of insulation completed
10/2021 – Start of painting the facade
11/2021 – Facade painting completed
12/2021 – Works on the foundations of the fence wall
01/2022 – Works on the fence wall
03/2022 – Works on landscaping the garden, interior works
05/2022 – Installation of stone pavers
08/2022 – Installation of ceramics and laminate