The Medulin Livadice A and B project is one of our newest projects in Medulin, and it is about the construction of two buildings, ie a duplex, in the immediate vicinity of the school, not far from our previous Medulin Plodine project. These are two smaller buildings, which are connected into one larger unit. Some of the advantages are garage parking spaces, close to the kindergarten and the Elementary School Medulin, from which the buildings are only a few minutes walk away. In addition to the proximity of schools and kindergartens, the buildings are located near the Medulin waterfront, which is separated by a ten minute walk.
- Square meters : 117-189m2
- Construction Completion Deadline : 2022

Close to public transport

Parking place

Air conditioning

Project Timeline
06/2020 – Beginning of foundation excavation
07/2020 – Preparations for raising the ground floor
11/2020 – Start of ground floor construction
12/2020 – Raising the ground floor
01/2021 – Completion of the ground floor, preparations for the start of the first floor
02/2021 – Start of construction of the first floor
03/2021 – Raising the first floor
04/2021 – Completion of the first floor of building B, start of construction of the second floor
04/2021 – Construction of the second floor of building B, preparations for the start of construction of the second floor of building A
05/2021 – Completion of the second floor of building B, erection of the second floor of building A
05/2021 – Works on the roof of building B, completion of the second floor of building A
06/2021 – Construction of building A completed, completion of roof works
10/2021 – Installation of PVC joinery
10/2021 – The beginning of landscaping
11/2021 – Works on the fence wall
12/2021 – Completed works on the fence wall, preparations for the start of insulation installation
01/2022 – Start of insulation installation
01/2022 – Installation of insulation for Building A
02/2022 – Completion of building insulation installation A
03/2022 – Completion of works on the facade of Building A
04/2022 – Works on installation of insulation and facade of Building B
05/2022 – Finished work on the facade
06/2022 – Works on installations
07/2022 – Plastering of apartments
10/2022 – Installation of ceramics
01/2023 – Completed installation of the screed, landscaping of the garden