Villa Park 3 project – Buildings 16 and 17
The Villa Park 3 project is another of our projects in Valdebek, and it is about the construction of a smaller settlement of fifteen buildings, located near our project “Valdebek – Modrušanov Prilaz”, and our project “Valdebek Villa Park 4”. The village is located in a quiet, great position, and close to two pizzerias, two markets and a bus station that takes you a ten minute drive to the center of Pula. Buildings 16 and 17 are one of the first buildings in this future settlement, as well as others that have begun construction, and they are smaller buildings with only a few apartments, which is ideal for those who like a smaller number of neighbors.
- Square meters : 43-107m2
- Construction completion deadline : 2021

Close to public transport

Parking

Air conditioning

Project Timeline
02/2021 – Beginning of earthworks and foundation works
03/2021 – Completed works on the foundations, start of ground floor construction
03/2021 – Raising the ground floor
03/2021 – Raising the ground floor, the works are going very quickly and according to plan, and we are moving forward quickly on this clean and tidy construction site.
04/2021 – Completion of ground floor erection
05/2021 – Raising the first floor
07/2021 – Continuation of the construction of the first floor
08/2021 – Concreting the second half of the first floor slab
09/2021 – Raising the second floor
10/2021 – Completion of the second floor
10/2021 – Second floor erection completed, concrete roof
12/2021 – Installation of PVC joinery
01/2022 – Installation of PVC joinery completed
02/2022 – Start of installation of insulation and facade
03/2022 – Completion of insulation installation
04/2022 – Silicate coating
06/2022 – Finished installation and painting of the facade