Project Kaštanjer ABC
The Kaštanjer ABC project is one of our latest projects in Kaštanjer, in Bože Gumpca Street, not far from Pula City Mall. These are 3 smaller buildings, each with only a few apartments, connected into one nice smaller block. The building is located in a beautiful position, across from our Bonus 3 project, and only about 500m from the shopping center Pula City Mall. Apart from the proximity of the shopping center, the building is not far from the shopping and business zone Pula, where there are several larger stores such as Lidl, Kaufland and Plodine.
- Square meters : 40-101m2
- Construction completion deadline : 2022

Close to public transport

Parking place

Air conditioning

Project Timeline
01/2021 – Earthworks, preparations for the start of construction
02/2021 – Start of construction of the first floor
02/2021 – Works on foundations
03/2021 – Casting the foundations of building B
03/2021 – Completed foundations of building B, start of works on the foundations of building A
03/2021 – Cast foundations of building A
March 29, 2021 – Start of construction of the ground floor of Building C, work is currently underway
01.04.2021 – Raising the ground floor of the block, work is underway and preparations for concreting
04/2021 – Concreting of ground floor walls
04/2021 – Completion of concreting, works on ground floor partitions
04/2021 – Preparations for the start of the construction of the first floor
05/2021 – Raising the first floor
06/2021 – Completion of the first floor
07/2021 – Preparations for the construction of the second floor
07/2021 – Raising the second floor
07/2021 – Completion of the construction of the second floor
07/2021 – Completed erection of the second floor, start of work on the roof
08/2021 – Roof works
08/2021 – Completed roof works
11/2021 – Commencement of works on the fence walls
11/2021 – Installed PVC joinery
11/2021 – Concreting of the fence wall
12/2021 – Completion of works on the fence wall
12/2021 – Plastering of apartments
01/2022 – Sewer connection works
02/2022 – Landscaping and paving works
03/2022 – Finishing plastering
05/2022 – Insulation installation work
06/2022 – Coating of silicate, works on the facade
07/2022 – Facade painting
08/2022 – Fertige Fassadenmalerei