Medulin Lokva – Buildings E and F
Medulin Lokva – Buildings E and F, is the latest part of our project of building a residential area of 14 buildings, located in a quiet beautiful location, only thirty meters from Lokva in Medulin. The buildings are near our project Medulin Plovanije A, B, C, D which is like this, a project to build a residential area, but with a few more buildings. Buildings E and F are the fourth smaller block of 2 buildings within the settlement of Medulin Lokva, and as with the previous 6 buildings, they are smaller buildings, with 2 floors and several apartments per building, which is great for fans of smaller buildings. The position is quiet and beautiful, near Medulin’s Lokva, which in itself is a beautiful sight. Apart from the proximity of Lokva, the Medulin waterfront and the beach, as well as all the facilities located on the waterfront – restaurants, shops, etc. are only a 20-minute walk away.
- Square meters : 49-103m2
- Construction completion deadline : 2021

Close to public transport

Parking place

Air conditioning

Project Timeline
10/2020 – Start of construction, earthworks
10/2020 – Works on foundations
11/2020 – Installed base plate
01/2021 – Start of ground floor construction
01/2021 – Raising the ground floor
02/2021 – Completion of the ground floor, preparation for the start of the first floor
02/2021 – Start of construction of the first floor
02/2021 – Raising the first floor
03/2021 – Erection of the second floor of the Building F
03/2021 – Works on the roof of the Building F
02.04.2021 – Works on the roof of Building F, the building is being prepared for concreting the roof
04/2021 – Concreting the roof of building F
05/2021 – Completion of works on the roof of building F, preparations for the start of construction of the first floor of building E
05/2021 – Start of installation of PVC joinery and insulation on the building F
05/2021 – Cast slab of the first floor of building E, installation of insulation of building F
06/2021 – Plastering of building F
06/2021 – Erection of the first floor of building E
07/2021 – Plastering of building F completed, facade painting
07/2021 – Finished painting of the facade of the building F
09/2021 – Completion of the first floor of Building E, concreting of the slab
10/2021 – Erection of the second floor of Building E
11/2021 – Completion of the second floor of Building E, roof works
11/2021 – Concreting the roof
02/2022 – Completed concreting and works on the roof
05/2022 – Installed PVC joinery
09/2022 – Works on concrete surfaces, interior works
11/2022 – Works on installation of insulation
01/2023 – Facade painting